Framingham DPW Announces Sewer Force Main Lining Project
FRAMINGHAM – The City of Framingham is announcing a critical infrastructure project to improve a section of the sewer force main connected to the Worcester Road Sewer Pump Station. Beginning Monday, July 21, construction crews will begin lining approximately 500 linear feet of 16-inch diameter sewer force main. The work is essential to extend the life of this key piece of sewer infrastructure.
Location and Scope of Work:
- The project will take place from the Worcester Road Sewer Pump Station (730 Worcester Road) to the edge of Main Street near the intersection with Walnut Street.
- Two access pits will be established: one at the Pump Station and the other on the shoulder of Main Street, near the intersection with Walnut Street.
Traffic Impacts:
- All traffic impacts will involve one-lane alternating traffic on Main Street near Walnut Street.
- There will be no traffic impacts on Route 9.
- Police details will be present throughout the construction to help manage traffic flow.
- Delays are expected, especially during peak hours. Drivers are encouraged to seek alternate routes and plan extra travel time.
Updated Construction Schedule:
- Monday, 7/21: Open access pit on Main Street; one-lane alternating traffic from 7 a.m. to 4 p.m.
- Tuesday, 7/22: Open access pit at the Worcester Road Pump Station; no traffic impacts.
- Thursday, 7/24: Dewatering, cleaning, and CCTV inspection; one-lane alternating traffic from 7 a.m. to 5 p.m.
- Friday, 7/25: Reserved as a weather contingency day.
- Monday, 7/28: Mobilization and pre-CCTV inspection; one-lane alternating traffic from 7 a.m. to 5 p.m.
- Tuesday–Wednesday, 7/29–7/30: Sewer liner installation, curing, and final dewatering; one-lane alternating traffic from 7 a.m. to 5 p.m., including overnight work from 7 p.m. Tuesday to 7 a.m. Wednesday.
- Thursday, 7/31: Installation of Weko seals and pressure testing; one-lane alternating traffic from 7 a.m. to 5 p.m.
- Friday, 8/1: Cleanup and demobilization; one-lane alternating traffic from 7 a.m. to 12 p.m.
Community Impact:
- Traffic delays are expected due to the lane reductions on Main Street.
- Night work on July 29–30 will help reduce daytime disruptions.
- Residents and commuters are encouraged to allow extra time for travel or use alternate routes when possible.
###