PROJECT OVERVIEW

The Department of Public Works will restore the roadway and sidewalks in the following locations:

  • Grant Street (between Arthur Street and Hartford Street)

This is the second of a two-phased project designed to mitigate motor vehicle accidents and enhance road safety for all users. In 2020, the first phase of this project was completed (between Clinton Street and Arthur Street).

This project is based upon recommendations from the 2018 Feasibility Study - Grant Street Neighborhood Complete Streets. Grant Street is an Environmental Justice area, and the improvements to the community include safer walking and biking networks and traffic calming at intersections. 

Work includes drainage improvements, milling and overlaying the pavement, sidewalk restoration with ADA Improvements, and traffic calming intersection improvements.

The majority of the work will take place during the daytime. A traffic management plan (TMP) for the work area will be implemented to ensure the safety of residents, traffic, and workers.

Consultant—BETA Group, Inc.
Contractor—Newport Construction

Project update

Drainage work is scheduled to begin the week of May 31.

For more information

The City of Framingham Department of Public Works seeks to minimize any inconveniences to residents while roadwork improvements are taking place. Please contact the Highway Division at 508-532-6030 with any questions or concerns.